Huck BOM (industrial)
Howmet/Huck · Blind bolt · BOM-R[dia]-[grip] · e.g. BOM-R8-6
speclok.com
11/16/2026
Install sequence
1. Inserted
2. Bulb forms
3. Collar swaged
4. Pin separates, tool ejects
Traced from Howmet Huck BOM brochure, p.3, Installation Sequence. Not to scale.
Before you install
- Diameters offered: 3/16, 1/4, 5/16, 3/8, 1/2, 0.625, 0.75"
- Tool: Huck installation tool ("push-and-pull installation", BOM brochure)
- Proprietary system required.
- Training: Not stated in the cited documents.
- Lead-time risk: Medium
Installed preload
Not published. Installed values are minimum ultimate shear/tensile only (tested at grip of at least 1.5x diameter).
Gauge kit (published part numbers)
| Gauge | Sizes | Checks / limits | Source |
|---|---|---|---|
| PB162 / PB509 | all | Huck gage bulletins (grip; pin position / swage) | Howmet Huck BOM brochure, p.4, Inspection Data |
Removal
No published removal procedure found; follow the manufacturer's instructions. Steps: speclok.com/tooling/huck-bom#removal
Accept / reject after install
- Pin separating near flush = correctly installed (stated completion criterion).
- Installed inspection dimensions published per diameter, 3/16" through 3/4" (brochure Inspection Data: swaged collar diameter, pin-break offset, blind-side bulb diameter, axial positions).
Check gauges
- Huck gage bulletins PB162 (grip) and PB509 (pin position / swage) apply; per-diameter tables not freely retrievable.
Sources: BOM brochure (Howmet). Acceptance limits belong to the controlling spec: verify against your program's process documentation before use on hardware.